1361 - Arts Village (Project Complete and Accepted March 2007)
Scope: Relocate four existing modular classrooms from the area of construction work of the Hourglass Park Fieldhouse. In accordance with the Campus Master Plan, the classrooms were placed adjacent to the Art Program to form an "Arts Village."
- Architect: Structural Design Consultants & Architects
- Construction Manager: Parsons
- General Contractor: EC Constructors
Project Costs
- Final Project Costs = $477,290
|