1351 - Infrastructure - Parking / Utilities / Clocktower
Project Delivery Method Design-bid-build
Project Budget $15,795,000
Construction Duration 2008-2009 Start Date 07.01.08
Scope / Summary
The Infrastructure Phase 1 project consists of renovated and new surface parking lots, road improvements, utility support to future buildings, new sidewalks, and landscaping over a majority of the campus.
Design has been completed with DSA approval obtained on February 13, 2008. Currently the Infrastructure Phase 1 project is being advertised and the anticipated bid opening date is May 6, 2008.
After bid opening and the identification of a successful bidding contractor, the SDCCD facilities staff will recommend award of a contract. It is anticipated to gain SDCCD Board approval in late May or mid June with a construction start in early June or July. The project is scheduled for completion in mid 2009.
- Architect: Wimmer Yamada & Caughey
- Construction Manager: Gafcon, Inc
|