1342 - Aviation Technology Career Instructional Building
Project Delivery Method: CMMP
Project Budget: $10.2 million
Construction Duration: 2010 – 2011
Scope/Summary
The Miramar Aviation Maintenance Building Technology Center project will repair and renovate the existing 15,300 SF building. This will include retrofit of existing classrooms and lab spaces and the construction of new classroom spaces.
Design Development began September 2009.
- Architect: Joseph Wong
- Construction Manager: Legacy Building Services
- Structural Engineeer: TMAD Taylor & Gaines
- Civil Engineer: T.B.D.
- Electrical Engineer: The Engineering Partners
- Mechanical/Plumbing Engineer: DEC Engineers
- Landscape Architect: T.B.D.
- Propositions S & N Program Manager: Gafcon, Inc.
- Campus Project Manager: Jim Bray, Gafcon, Inc.
- Assistant Campus Project Manager: Tyler Campbell, Gafcon, Inc.