1315 - Construct Arts and Humanities Building

Project Delivery Method              Design-bid-build (CM Multiple Prime)

Project Budget                           $22.4 million     

Construction Duration                 2009 – 2010

 

Scope / Summary

 

This project consists of approximately 30,480 square feet of new building construction for the eventual utilization by the Miramar College for a variety of purposes. the new building will include classroooms, studios, laboratories, lecture halls, and faculty offices and work area.

 

DSA approval was obtained on November 18m 2008. Project is currently bidding.

  • Architect: Sundt
  • Construction Manager: T.B.D.