1253 - Temporary Parking and All Weather Track and Field Projects

Delivery Method:                T.B.D
Project Budget:                  $64.1M

Scope / Summary

The 551 space temporary parking lot was completed in 1/08 within its $800,000 budget.

Upon completion of the East Campus Improvement Project, (Road realignment, construction of a parking structure and construction of police station),  the temporary parking lot will be demolished and the all-weather track and field project will commence in March 2009 with completion by September 2009.  The $7.1 million project will be designed by a to-be-selected company with the URS Corp. providing CM services
.

  • Architect: Delawie Wilkes Rodrigues Barker Architects
  • Construction Manager: URS Corp.
  • Contractor: Ramona Paving 